The chassis is 99%
complete... Yes, my car now has front disc brakes! The only things left to do on it are replace the rear
emergency brake cables with new stainless ones and put stainless
braided brake lines on the front. Joe will be blasting/painting
the steering box tonight and putting it back on.
-
The radiator support is
done.
-
The aluminum radiator came
in and I got my transmission back from the shop.
-
The engine parts are all
being ordered tomorrow, so the engine should be done the week of
January 10th.
-
Once I have the drivetrain
components put together, they will be installed on the rolling
chassis.
-
Other notable parts that
are coming in the next few days: Mighty Demon 850 carburetor
& the Centerforce II high performance clutch.
-
Other notable parts that
are in: The correct driver's side door skin. 3"
exhaust system with "X" crossover & high performance
mufflers. The headers should be in this week. The ENTIRE
exhaust system is ceramic coated. The hood & rear bumper
came in a couple of weeks ago. Too many other parts to list have
come in.
-
Due to the snowstorm a
week ago, my body is not back from the media blasting place yet.
It should be back over the next couple of days.
-
Scheduled for this
week: Get the body back. Finish up the chassis. The
body work should be completed on the passenger side fender & both
doors. All should be in primer and ready for painting when the
body is done.